Yonge Street rapidway - Richmond Hill:
Paving, side-street closures, starting July 10



Update — Tuesday, July 23, 11:08 a.m.: The contractors are setting up a temporary work zone blocking Nottingham Drive at Yonge Street from 7 a.m. Wednesday, July 24 until 7 p.m. Thursday, July 25.


Update — Friday, July 19, 7:04 p.m.: The contractors are setting up temporary work zones blocking the side streets starting the week of July 22. First: Canyon Hill Avenue from 7 a.m. Monday, July 22 until 7 p.m. Tuesday, July 23.


Update — Wednesday, July 17, 12:24 p.m.: The contractors will not be setting up temporary work zones blocking Nottingham, Devonsleigh, Silverwood, Oxford and Trayborn at Yonge Street this week. Metrolinx and vivaNext will reschedule the closures.


Update — Monday, July 15, 9:11 a.m.: Metrolinx and vivaNext have cancelled the closure of Canyon Hill Avenue tonight.


Update — Friday, July 12, 3:36 p.m.: Metrolinx and vivaNext have rescheduled the closure of Canyon Hill Avenue to 7 a.m. Monday, July 15 until 7 p.m. Tuesday, July 16.


VivaNext - Yonge - Richmond Hill - header.jpg

Metrolinx and York Region contractors continue the project to build a rapidway — bus-only lanes in the centre of the roadway — along Yonge Street in Richmond Hill between 19th Avenue / Gamble Road and Highway 7.


Over the next few weeks, crews are setting up work zones that temporarily block side streets

  • east and west of Yonge Street between Gamble Road / 19th Avenue and Trayborn Drive.

The work zones accommodate road reconstruction and paving and block motorists from entering or exiting the side streets to and from Yonge.


(Updated — Friday, July 12, 3:36 p.m.) (Updated — Monday, July 15, 9:11 a.m.) (Updated — Friday, July 19, 7:04 p.m.) (Updated — Tuesday, July 23, 11:08 a.m.)

  • Brookside Road: 7 a.m. Wednesday, July 10 until 7 p.m. Thursday, July 11.
  • Canyon Hill Avenue: 7 a.m. Friday, July 12 until 7 p.m. Saturday, July 13 Monday, July 15 until 7 p.m. Tuesday, July 16.
  • Nottingham Drive: 7 a.m. Monday, July 15 until 7 p.m. Tuesday, July 16.
  • Devonsleigh Boulevard: 7 a.m. Wednesday, July 17 until 7 p.m. Thursday, July 18.
  • Silverwood Avenue: 7 a.m. Monday, July 23 until 7 p.m. Tuesday, July 24.
  • Oxford Street: 7 a.m. until 7 p.m. Wednesday, July 25.
  • Trayborn Drive: 7 a.m. until 7 p.m. Thursday, July 26.

  • Canyon Hill Avenue: 7 a.m. Monday, July 22 until 7 p.m. Tuesday, July 23.

  • Nottingham Drive: 7 a.m. Wednesday, July 24 until 7 p.m. Thursday, July 25.

Crews maintain access to businesses and properties near the work zones.

Traffic-control personnel will be on-site to direct traffic during this work.

Expect noise and dust from equipment and trucks.

York Region Transit may temporarily relocate bus stops near work zones. Passengers aboard buses along these routes can also expect delays:

  • Viva blue;
  • Viva blue “A”;
  • 81 Inspiration;
  • 83 Trench;
  • 86 Newkirk - Red Maple;
  • 98 Yonge;
  • 98E Yonge express;
  • 98 / 99 Yonge late-night;
  • 99 Yonge;
  • 589 / 590 Richmond Hill local.