Eglinton Crosstown LRT - Surface section:
"Guideway" construction at Don Valley Parkway



Update — Monday, July 15, 10:17 p.m.: The contractors have postponed the work until Friday, July 26.


Eglinton Crosstown header.jpg

Metrolinx contractors continue building the future Eglinton Crosstown light rail transit line between Mount Dennis and Kennedy.


Crews are building the LRT “guideway” — the transit-only lanes in the centre of the roadway, including tracks and passenger amenities

  • on Eglinton Avenue East at the Don Valley Parkway (DVP)

between the sites of the future Wynford and Aga Khan stops.

(Updated — Monday, July 15, 10:17 p.m.) Since March, crews have been working at the west side of the Parkway — near the on- and off-ramps for the southbound DVP. “As early as” Friday, July 12 July 26, they start working at the east side of the Parkway, near the northbound ramps.

Recently, to accommodate upcoming changes to traffic lanes, crews have been building a temporary off-ramp from the northbound DVP to eastbound Eglinton East.

During guideway construction east of the Parkway, crews are:

  • cutting and removing asphalt;
  • excavating;
  • installing “subgrade materials” (compacted soil to form the base for a pavement);
  • installing duct banks, track drainage, the track slab and tracks.

2019 - 07-12 - Don Valley Parkway - guideway construction.jpg

Guideway construction east of the DVP and the resulting TTC service changes continue until December 31, 2020.


For transit passengers

  • Expect delays aboard TTC buses along these routes:
  • 34 Eglinton East; and
  • 334 Eglinton East overnight.

For pedestrians

  • Starting Friday, July 12, the north-south crosswalk on Eglinton at the ramps to and from the southbound Parkway reopens.
  • Starting Friday, July 12, the north-south crosswalk on Eglinton at the ramps to and from the northbound Parkway closes.

For motorists

  • Starting Friday, July 12, a temporary off-ramp from the northbound DVP to westbound Eglinton — west of the permanent ramp — opens. The permanent off-ramp is closed.
  • Starting Friday, July 12, the permanent off-ramp from the southbound DVP to eastbound Eglinton reopens. The temporary off-ramp is closed.
  • Work zones block centre lanes from west of the ramps to and from the southbound Parkway to east of the northbound DVP ramps, except for gaps to allow traffic on the ramps to exit onto Eglinton.
  • Two lanes are available for traffic in both directions on Eglinton east and west of the DVP.