Eglinton Crosstown LRT - Sloane:
Intermittent crosswalk closures



Update — Monday, March 11, 11:57 a.m. — Since the contractors are starting another phase of the project tomorrow that blocks one of the crosswalks continuously overnight from 7 p.m. until 6 a.m. expect most of the construction activity that this post describes to take place before 7 p.m. until March 17.


Eglinton Crosstown header.jpg

Metrolinx contractors continue building the future Eglinton Crosstown light rail transit line between Mount Dennis and Kennedy.


“As early as” Monday, March 11, crews expand the work zone

  • at the intersection of Eglinton Avenue West with Sloane Avenue / Bermondsey Road, southeast corner,

to continue installing new utility lines near the site of the future Sloane stop.

During this stage of the project, crews may intermittently block two crosswalks at the intersection to maintain pedestrian safety:

  • the north-south walk on the east side of Bermondsey / Sloane at Eglinton East; and
  • the east-west walk on the south side of Eglinton at Bermondsey.

Crews maintain access to three of the four crosswalks at all times. They’ll also install signs to direct you to available crosswalks at the intersection.

Crews work every day from 7 a.m. until 11 p.m.

2019 - 03-11 - Sloan - crosswalk closures - Bermondsey.jpg

Intermittent crosswalk closures near the future Sloane stop continue “for approximately two (2) weeks” or until about March 24.


For transit passengers

  • The TTC has relocated its eastbound stop on Eglinton East west of Bermondsey to a temporary platform beside the work zone.
  • During ongoing construction of the future Sloane stop, xpect delays aboard buses along these routes:
  • 34 Eglinton East;
  • 91 Woodbine; and
  • 334 Eglinton East overnight.

For pedestrians

  • From Monday, March 11 until Sunday, March 24, crews may intermittently block the north-south crosswalk on the east side of Bermondsey / Sloane at Eglinton East and the east-west walk on the south side of Eglinton at Bermondsey. Crews maintain access to three of the four crosswalks at all times.

For motorists

  • Work zones block eastbound curb lanes on the south side of Eglinton east and west of Bermondsey.
  • The work zone east of Bermondsey blocks northbound curb lanes on the east side of Bermondsey south of Eglinton.
  • At least two lanes are available for traffic in both directions on Eglinton.
  • Just one through lane is available for northbound through traffic on Bermondsey. Two lanes are also available so that northbound traffic can turn left onto westbound Eglinton.
  • Just one through lane is available for southbound traffic on Sloane / Bermondsey.