Eglinton Crosstown LRT - Mount Pleasant:
Overnight road closure, TTC detour



Eglinton Crosstown header.jpg

Metrolinx contractors continue building the future Eglinton Crosstown light rail transit line between Mount Dennis and Kennedy.


From 9 p.m. Monday, November 4 until 5 a.m. Tuesday, November 5, the City of Toronto is closing

  • Mount Pleasant Road between Roehampton Avenue and Eglinton Avenue West

to accommodate the Metrolinx contractors who are installing a new traffic bridge at the site of the future Mount Pleasant Station.

The crews are installing the temporary traffic bridge on the northeast corner of Mount Pleasant Road and Eglinton Avenue East. The temporary traffic bridge allows crews to work on both corners of the intersection, while traffic travels safely over top. They’re also erecting a mobile crane in the Mount Pleasant roadway.

Northbound traffic on Mount Pleasant must turn left or right onto Eglinton East during the closure. Southbound traffic must turn left or right onto Roehampton Avenue.

The TTC is also detouring buses, while the street is closed.

2019 - 11-04 - Mount Pleasant - Overnight traffic bridge installation.png


For transit passengers

  • The TTC is detouring buses along this route, while the street is closed:
  • 74 Mount Pleasant.

74_MtPleasantRd_Cros.gif

  • It’s already relocated stops in the area and may temporarily further relocate stops near work zones.
  • Expect delays aboard buses along these routes:
  • 34A / 34C Eglinton East;
  • 54A / 54B Lawrence East;
  • 56 Leaside;
  • 51 Leslie;
  • 334 Eglinton East overnight;
  • 354 Lawrence East overnight.

For pedestrians

  • A work zone blocks the sidewalk on the north side of Eglinton west of Mount Pleasant. A temporary walkway leads you around the work zone. The temporary walkway is south of the work zone on a closed portion of the roadway. Safety barriers protect you from traffic.
  • A work zone blocks the east end of the east-west crosswalk on the north side of Eglinton. A temporary walkway leads you around the work zone. The temporary walkway is west of the work zone on a closed portion of the roadway. Safety barriers protect you from traffic.
  • The north-south crosswalk on the east side of Mount Pleasant at Eglinton remains open.
  • The north-south crosswalk on the west side of Mount Pleasant at Eglinton remains closed.

For motorists

  • From 9 p.m. Monday, November 4 until 5 a.m. Tuesday, November 5, Mount Pleasant Road is closed to traffic between Roehampton Avenue and Eglinton Avenue East. “Paid-duty” Toronto Police Service officers and traffic-control personnel will be on-site to direct traffic.
  • Work zones block traffic lanes on the north side of Eglinton East east and west of Mount Pleasant.
  • A work zone continues to block the northbound curb lanes on Mount Pleasant south of Eglinton.
  • An “island” work zone blocks the centre lanes of Eglinton east and west of Taunton Road.
  • Just one lane is available for traffic in both directions on the south side of Eglinton East west of Mount Pleasant.
  • Just one lane is available for traffic in both directions on Eglinton East east of Mount Pleasant. Traffic flows on the south side just east of Mount Pleasant. East of Taunton, traffic flows in the east- and westbound curb lanes.
  • Just one lane is available for traffic in both directions on the west side of Mount Pleasant south of Eglinton East.
  • Two lanes are available for traffic in each direction on Eglinton east of Rawlinson Avenue and west of Brownlow Avenue.
  • A work zone continues to block access to Rawlinson at Eglinton East.
  • You can’t turn left from northbound Brownlow and Taunton to westbound Eglinton.

For nearby residents and business people

  • Expect overnight noise from construction equipment, such as an excavator, hydro-vacuum, trucks and a generator.
  • Expect overnight site lighting.

74 Mount Pleasant

From 9 p.m. Monday, November 4 until 5 a.m. Tuesday, November 5, southbound buses operate along their regular route to Mount Pleasant Road and Roehampton Avenue, then detour:

westward along Roehampton;
southward along Redpath Avenue; and then
eastward along Soudan Avenue to Mount Pleasant,
resuming their regular route southward along Mount Pleasant.

Southbound buses skip their regular stop

  • on Mount Pleasant Road at Soudan Avenue.

Instead, southbound buses drop off or pick up passengers at a temporary stop

  • on Redpath Avenue at Eglinton Avenue East.

Northbound buses operate along their regular route to Mount Pleasant Road and Eglinton Avenue East, then detour:

westward along Eglinton East;
northward along Redpath Avenue; and then
eastward along Broadway Avenue to Mount Pleasant,
resuming their regular route northward along Mount Pleasant.

Northbound buses skip their regular stops

  • on Mount Pleasant Road at Roehampton and Broadway Avenues.

Instead, northbound buses drop off or pick up passengers at temporary stops

  • on Redpath Avenue north of Eglinton Avenue East and Roehampton Avenue and at Broadway Avenue.