TTC temporarily closing Fieldway parking lot
at Islington Station, starting April 3



Update — Tuesday, September 5, 10:22 p.m.: Construction continues until November 4 to accommodate the Hydro One / Toronto Hydro project


Starting Monday, April 3, the TTC is temporarily closing its commuter parking lot at 22 Fieldway Road, near Islington Station, as crews upgrade the lot.

While the lot is closed, crews are installing:

  • a new asphalt surface;
  • better lighting;
  • paved concrete paths;
  • landscaping; and
  • seven accessible parking stalls.

(Updated — Tuesday, September 5, 10:22 p.m.) Hydro One and Toronto Hydro, are significantly upgrading their power infrastructure in west-end Toronto. They’re improving the transmission line through TTC parking lots in the area. The Fieldway parking lot continues to be closed until November 4 as a part of this work.

During construction, please use other commuter lots near Islington Station or at nearby Kipling Station.

Construction at the Fieldway lot continues until August 31 November 4.