Finch Station east commuter parking lot:
Phase 2 of TTC construction starts January 6



Update — Wednesday, May 10, 9:04 a.m.: Saturday, May 13, Sunday, May 14, Saturday, May 20, Sunday, May 21 and Victoria Day, Monday, May 22, the TTC is closing the east commuter lot for paving. Use the west commuter lot.


Starting Friday, January 6, TTC contractors start phase 2 of a project to repave the east commuter parking lot at Finch Station, including:

  • resurfacing the parking lots;
  • improving the drainage systems;
  • improving the lighting system by installing LED energy-efficient lights; and
  • increasing the number of accessible parking spaces.

To keep the lot open for passengers, the TTC has phased construction work. Less parking will be available in the lot during the various stages of work. The TTC maintains access to the lot, except when crews are repaving areas near access points. It has removed the parking-lot gates and replaced them with temporary “pay and display” meters during construction.

During stage 1, starting Monday, August 15, 2016, construction crews reduced the Willowdale Avenue driveway access to just two lanes of traffic. The crews required one lane for access.

During stage 2, the crews reduce the Yonge Street driveway access to just two lanes of traffic.

During each stage of work, only about half of the parking spaces are available for you to use. However, more space is available in the west commuter lot at Finch Station.

Crews mostly work from 7 a.m. to 7 p.m. every day, although from time to time, they may work after these hours to complete the work as quickly as possible.

Expect noise and vibration.

Construction in the east commuter parking lot at Finch Station continues until December 31.