Davis Drive rapidway construction blocks lanes
at Yonge and Davis, starting December 10



Metrolinx and York Region contractors are working on the project to build a rapidway — bus-only lanes in the centre of the roadway — along Davis Drive in Newmarket.

Starting today, Monday, December 10, from about 7 a.m. until 4 p.m. each day, they’ll be working on the underground utilities work at the intersection of Yonge Street and Davis Drive.

During this phase of the project, work crews will dig a pit and send a tunneling machine under the road at four separate locations, one at a time. (The crews will generally work segment by segment in the sequence that the numbers on the map indicate.)

yonge-davis - dec10-21 - 12.jpg

Each tunneling segment requires about two to three days. Work continues until December 21.

Passengers riding GO Transit buses operating along the 65 Newmarket / Toronto and 68 Barrie / Newmarket routes and York Region Transit buses operating along the Viva blue, 50 Queensway, 52 Holland Landing, 55 / 55B Davis Drive, 58A Leslie via Mount Albert, 98 Yonge and 520 / 521 Newmarket community bus routes should expect delays.