Transit Toronto reader Dave Fisher e-mailed us again to let us know that the TTC continued with its project to repair the tracks on the Bathurst Street bridge south of Front Street West yesterday, Thursday, March 11.
Although the TTC’s website alerts passengers that the work started at 7 p.m. March 11 and only continues until 6 a.m. today, Friday, March 12, the work may still require the TTC to detour streetcars until later today and you should plan to add extra time to your trip.
511 Bathurst
From 7 p.m. on Thursday, March 11 until 5 a.m. on Friday, March 12, southbound streetcars operate along their regular route to Bathurst Street and King Street West, then detour:
eastward along King West;
southward along Spadina and Lower Spadina Avenues;
westward along Queens Quay West; and then
northward along Bathurst Street to Fleet Street,
resuming their regular route westward along Fleet.Southbound cars skip their regular stops on Bathurst Street at Wellington and Front Streets West and Fort York Boulevard.
Northbound cars reverse this routing.
Northbound cars skip their regular stops on Bathurst Street opposite Fort York Boulevard, north of Front Street West and at Wellington and King Streets West.
310 Bathurst overnight
Buses continue to operate along their regular route through the construction zone.